6The Project layout

This chapter tells you how to use the Project layout. This layout has the same parts as Microsoft Project.

Parts of the Project layout

PartWhereUse
File tabTop leftOpen, save, import, export and print (the Backstage view)
RibbonTopTask, Resource, Report, Project, View and Format tabs
TimelineBelow the ribbonA summary of the project dates
Task sheetLeftOne row for each task
Gantt chartRightOne bar for each task
Status barBottomThe mode for new tasks, and the view buttons
The Project layout with the ribbon, the task sheet and the Gantt chart
Figure 6-1. The Project layout.

Make the tasks

To add a task

  1. Click the first empty row of the task sheet.
  2. Type the Task Name and push Enter.
  3. Type the Duration, for example 5d or 2w.

To make a milestone, click Task › Milestone, or type a duration of 0d.

To make a summary task

  1. Select the tasks below the summary row.
  2. Push Alt+Shift+→, or click the indent button on the Task tab.The row above becomes a summary task. Its bar starts at the first task and ends at the last task.

To link tasks

  1. Select the tasks in the sequence of the work.
  2. Push Ctrl+F2, or click the link button on the Task tab.Each task becomes the predecessor of the next task (Finish-to-Start).

You can also type the predecessors in the Predecessors column, for example 4FS+2d.

Auto scheduled and manually scheduled tasks

An auto scheduled task gets its dates from the logic and the calendar. A manually scheduled task keeps the dates that you type. The scheduler does not move it.

To change the mode, select the tasks and click Task › Auto Schedule or Task › Manually Schedule. The mode for new tasks shows on the status bar.

The P6 layout and the 4D layout show a manually scheduled task as an activity with fixed dates. If you export the project to XER, P6 schedules the task as usual.

Task information

Double-click a task, or push Shift+F2, to open the Task Information dialog. The dialog has these tabs: General, Predecessors, Resources, Advanced, Notes and Custom Fields.

The Task Information dialog
Figure 6-2. The Task Information dialog.

On the Advanced tab, you set the Deadline, the Constraint type, the Task type and Effort driven.

Work, duration and units

When you assign a resource to a task, the Project layout uses this rule: Work = Duration × Units. The task type tells which value stays the same when you change a different value. Figure 6-3 shows the three task types.

Work = Duration × Units The task type tells which value stays fixed when you change one of the others. Fixed Units Change Duration → Work changes Change Units → Duration changes Change Work → Duration changes Default. The crew size stays the same. Fixed Duration Change Duration → Work changes Change Units → Work changes Change Work → Units change For a curing time or a hire period. Fixed Work Change Duration → Units change Change Units → Duration changes Change Work → Duration changes With Effort driven: add a resource,the same work ends sooner.
Figure 6-3. Work, duration and units for each task type.

To assign a resource

  1. Select the task.
  2. Click Resource › Assign Resources.
  3. Select the resource and type the units, for example 200% for two persons.
  4. Click Assign, then Close.

To see the work of each resource for each day, click View › Task Usage or View › Resource Usage. To see the resources as rows with their tasks, click View › Team Planner.

The Task Usage view
Figure 6-4. The Task Usage view, with the work for each day.
The Team Planner view
Figure 6-5. The Team Planner view.

A resource that has too much work shows in red. To find it, click Resource › Next Overallocation. To solve it, click Resource › Level All. To remove the result of the levelling, click Resource › Clear Leveling.

Calendars

To change the work hours and the holidays

  1. Click Project › Change Working Time.
  2. Select the calendar.
  3. To add a holiday, type a Name, a Start and a Finish on the Exceptions tab.
  4. To change the work week, use the Work Weeks tab.
  5. Click OK.
The Change Working Time dialog
Figure 6-6. The Change Working Time dialog.

Split tasks and repeated tasks

To stop a task and start it again later, click Task › Split Task. Then click in the bar at the point of the stop. The task gets a gap of one day at that point. Drag the second part of the bar to the new start date.

To add a task that occurs at regular intervals, for example a weekly progress review, click Task › Recurring Task. Type the pattern and the number of occurrences.

Baseline and progress

To set the baseline

  1. Click Project › Set Baseline.
  2. Select Entire Project or Selected Tasks.
  3. Click OK.

To update the project to a status date

  1. Click Project › Update Project.
  2. Select Update work as complete through and type the date.
  3. Click OK.The tasks before the date show as complete. The tasks that cross the date show as in progress.

To record the progress of one task, select the task and click Task › Mark on Track, or type the % Complete in the task sheet.

Save for Microsoft Project

To make a file for Microsoft Project, click File › Save As and select Save as MS Project XML. Microsoft Project opens this file directly.

Save As in the File tab
Figure 6-7. Save As in the File tab.
The XML file keeps the tasks, the summary tasks, the logic, the calendars, the resources, the assignments, the baseline and the custom fields.
← 5. The P6 layout7. The 4D layout →