8Dashboards and reports

This chapter tells you how to make a dashboard, change it, and send it as a PDF, Excel or PowerPoint report.

Open the Reports view

Click Reports on the layout switch at the top of the window, or push Ctrl+Alt+4. In the P6 layout, you can also click Reports and Dashboards in the menu.

The left column shows your dashboards. Below them, under New, are the Dashboard wizard… and the templates.

The Reports view with the list of templates
Figure 8-1. The Reports view before you make a dashboard.
TemplateContents
Project control – summaryKey dates, weighted %, durations and a table by discipline
Project control – S-curveWeight % curves with monthly bars, slicers and a date slider
Planning dashboardGauges, milestones, look-ahead and curves for each phase
Progress report (EPC style)Key figures, weighted progress and S-curve
Project statusKPIs, S-curve, critical work and late work
Schedule health and executionBEI, CPLI, SPI(t), PPC, starts and finishes on time, and the DCMA 14-point checks
Blank dashboardNo widgets. You add them from the widget gallery.

Make a dashboard with the wizard

The wizard makes sure that the data is ready before it makes the dashboard. Figure 8-2 shows the steps.

Dashboard wizard, then the outputs 1 Projectopen or saved 2 Baselineto compare with 3 Templateor blank 4 Checkprerequisites Dashboard Customise: widgets, slicers, page and theme PDF Excel PowerPoint Email A widget that compares with a baseline shows "Needs a baseline" until step 4 passes. Email on a schedule needs the desktop application or Stratum Server.
Figure 8-2. From the wizard to the reports.
  1. Open the project that you want to report on.
  2. Click Dashboard wizard….
  3. At Project, select the project. Click Next.
  4. At Baseline, select the baseline to compare with. Click Next.
  5. At Template, select a template, or Blank dashboard. Click Next.
  6. At Check, read the result of each check.Each check shows what to do if it does not pass.
  7. Click Create dashboard, or Create anyway.The dashboard opens, ready for changes.
The Template step of the dashboard wizard
Figure 8-3. The Template step of the dashboard wizard.

The wizard does a check of the baseline, the data date, the calculation, the progress, the costs and the logic. If a check does not pass, the button changes to Create anyway. Then the widgets that compare with the baseline show Needs a baseline, not incorrect numbers.

To make a dashboard without the wizard, click a template in the left column. To change the project or the baseline later, click More › Setup: project and baseline….

Read a dashboard

A Project status dashboard
Figure 8-4. A dashboard made from the Project status template.

Change a dashboard

  1. Click Customise.The panel on the right shows the Add widget and Page & theme tabs.
  2. To add a widget, click it in the Add widget tab. If the panel shows a widget, click Add / Page first.
  3. To move a widget, drag its handle at the top left.
  4. To change the size of a widget, drag its bottom right corner.
  5. To change the data of a widget, click the widget. Then change its settings in the panel.
  6. To change the header, the logo and the colors, use the Page & theme tab.
  7. Click Done.
A dashboard in edit mode, with the widget gallery
Figure 8-5. A dashboard in edit mode, with the widget gallery on the right.

Stratum 4D saves each change immediately. To go back one step, push Ctrl+Z.

To use a dashboard again

Make a report

ClickResult
PDFThe print dialog. Select "Save as PDF" to make a PDF file.
ExcelAn Excel workbook with the data of each widget
PowerPointA presentation with a title slide and one slide for each chart or table. The charts and tables are PowerPoint charts and tables, so you can change them.
EmailThe Email reports panel

Send reports by email on a schedule

The desktop application or Stratum Server can send a dashboard by email each day, week or month. The web application cannot do this. In the web application, make the PDF or the Excel file and send it yourself.

The desktop application sends the email only while it is open. If it was closed at the time of a send, it sends the email the next time you start it.

To set the mail server

  1. Open Settings.
  2. Click the Email tab.
  3. Type the data of your mail server. Your IT department can give you this data.

To add an email schedule

  1. Open the dashboard and click Email.
  2. Click + New email schedule.
  3. Type the Name and select the Project (reports need a saved project).
  4. In To (separate with ; or ,) and Cc, type the email addresses.
  5. Type the Subject and the Message. You can use {project}, {date} and {datadate} in the text.
  6. Select Daily, Weekly or Monthly, and the time.
  7. Select PDF of the dashboard, Excel workbook or the two.
  8. Make sure that Enabled is selected. Click Save schedule.

Each schedule shows the time of the next send and the result of the last send. To send a report immediately, click send now on the schedule.